Data centers need electricity fast, but utilities need years to build power plants – who should pay?

  • Written by Theodore J. Kury, Director of Energy Studies, University of Florida

The amount of electricity data centers use in the U.S. in the coming years is expected to be significant[1]. But regular reports of proposals for new ones[2] and cancellations of planned ones[3] mean that it’s difficult to know exactly how many data centers will actually be built and how much electricity might be required to run them.

As a researcher of energy policy who has studied the cost challenges[4] associated with new utility infrastructure, I know that uncertainty comes with a cost. In the electricity sector, it is the challenge of state utility regulators[5] to decide who pays what shares of the costs associated with generating and serving these types of operations, sometimes broadly called “large load centers[6].”

States are exploring different approaches, each with strengths, weaknesses and potential drawbacks.

A new type of customer?

For years, large electricity customers such as textile mills[7] and refineries[8] have used enough electricity to power a small city.

Moreover, their construction timelines were more aligned with the development time of new electricity infrastructure. If a company wanted to build a new textile mill[9] and the utility needed to build a new gas-fired power plant[10] to serve it, the construction on both could start around the same time. Both could be ready in two and a half to three years[11], and the textile mill could start paying for the costs necessary to serve it.

Modern data centers use a similar amount of electricity but can be built[12] in nine to 12 months. To meet that projected demand, construction of a new gas-fired power plant, or a solar farm with battery storage, must begin a year – maybe two – before the data center breaks ground.

During the time spent building the electrical supply, computing technology advances, including both the capabilities and the efficiency of the kinds of calculations artificial intelligence systems require. Both factors affect how much electricity a data center will use[13] once it is built.

Technological, logistical and planning changes mean there is a lot of uncertainty about how much electricity a data center will ultimately use. So it’s very hard for a utility company to know how much generating capacity to start building.

A large industrial site with two tall smokestacks.
Keeping older coal plants running may be an expensive way to generate power. Ulysse Bellier/AFP via Getty Images[14]

Handling the risks of development

This uncertainty costs money: A power plant could be built in advance, only to find out that some or all of its capacity isn’t needed[15]. Or no power plant is built, and a data center pops up, competing for a limited supply of electricity[16].

Either way, someone needs to pay – for the excess capacity or for the increased price of what power is available. There are three possible groups that might pay: the utilities that provide electricity, the data center customers, and the rest of the customers on the system.

However, utility companies have largely ensured their risk is minimal. Under most state utility-regulation processes[17], state officials review spending proposals from utility companies to determine what expenses can be passed on to customers. That includes operating expenses such as salaries and fuel costs, as well as capital investments, such as new power plants and other equipment.

Regulators typically examine whether proposed expenses are useful for providing service to customers and reasonable for the utility to expect to incur. Utilities have been very careful to provide their regulators with evidence about the costs and effects of proposed data centers to justify passing the costs of proposed investments in new power plants along to whomever the customers happen to be.

Regulators, then, are left to equitably allocate the costs to the prospective data center customers and the rest of the ratepayers, including homes and businesses. In different states, this is playing out differently.

Kentucky’s approach to usefulness

Kentucky is attempting to address the demand uncertainty by conditionally approving two new natural gas-fired generators[18] in the state. However, the utility companies – Louisville Gas & Electric and Kentucky Utilities – must demonstrate that those plants will actually be needed and used. But it’s not clear how they could do that, especially considering the time frames involved.

For instance, suppose the utility has a letter of agreement or even a contract with a new data center or other large customer. That might be sufficient proof for the regulator to approve charging customers for the costs of building a new power plant.

But it’s not clear what would happen if the data center ends up not being built, or needing much less power than expected. If the utility can’t get the money from the data center company – because they bill customers based on actual usage – that leaves regular consumers on the hook.

A large rectangular building.
A data center in Columbus, Ohio, is just one of many being built or proposed around the country. Eli Hiller/For The Washington Post via Getty Images[19]

Ohio’s ‘demand ratchet’ and credit guarantee

In Ohio, the major power company AEP has a specific rate plan for data centers[20] and other large electricity customers. One element, called a “demand ratchet,” is designed to mitigate month-to-month uncertainty in electricity consumption by data centers. The data center’s monthly bill is based on the current month’s demand or 85% of the highest monthly demand from the previous 11 months – whichever is higher.

The benefit is that it protects against a data center using huge amounts of electricity one month and very little the next, which would otherwise yield a much lower bill. The ratchet helps ensure that the data center is paying a significant share of the cost of providing enough electricity, even if it doesn’t use as much as was expected.

This ratchet effectively locks in the data center’s payments for 12 months, but regulators might expect a longer commitment from the center. For instance, Florida’s utilities regulator has approved[21] an agreement[22] that would require a data center company to pay for 70% of the agreed-upon demand in their entire electricity contract, even if the company didn’t use the power.

Another aspect of Ohio’s approach addresses the risk of changing business plans or technology. AEP requires a credit guarantee, like a deposit, letter of credit or parent company guarantee of payment, equal to 50% of the customer’s expected minimum bill under the contract. While this theoretically reduces the risk borne by other customers, it also raises concerns.

For example, a utility may not end up signing contracts directly with a large, well-known, wealthy technology company but with a subsidiary corporation with a more generic name – imagine something like “Westside Data Center LLC” – created solely to build and operate one data center. If the data center’s plans or technology changes, that subsidiary could declare bankruptcy, leaving the other customers with the remaining costs.

Harnessing strength in flexibility

A key advantage to these new types of customers is that they are extremely nimble in the way they use[23] electricity.

If data centers can make money based on their flexibility[24], as they have in Texas, then a portion of those profits can be returned to the other customers that shared the investment risk. A similar mechanism is being implemented in Missouri[25]: If the utility makes extra money from large customers, then 65% of that revenue increase is returned to the other customers.

Change is coming to the U.S. electricity system, but nobody is sure how much. The methods by which states are trying to allocate the cost of that uncertainty vary, but the critical element is understanding their respective strengths and weaknesses to craft a system that is fair for everyone.

References

  1. ^ expected to be significant (www.energy.gov)
  2. ^ proposals for new ones (news.constructconnect.com)
  3. ^ cancellations of planned ones (www.utilitydive.com)
  4. ^ studied the cost challenges (theconversation.com)
  5. ^ state utility regulators (www.naruc.org)
  6. ^ large load centers (www.reuters.com)
  7. ^ textile mills (www.etextilecommunications.com)
  8. ^ refineries (blog.se.com)
  9. ^ textile mill (shawinc.com)
  10. ^ gas-fired power plant (www.eia.gov)
  11. ^ two and a half to three years (bush.tamu.edu)
  12. ^ can be built (dgtlinfra.com)
  13. ^ electricity a data center will use (www.pewresearch.org)
  14. ^ Ulysse Bellier/AFP via Getty Images (www.gettyimages.com)
  15. ^ some or all of its capacity isn’t needed (www.utilitydive.com)
  16. ^ competing for a limited supply of electricity (ceea.us)
  17. ^ state utility-regulation processes (www.ourenergypolicy.org)
  18. ^ approving two new natural gas-fired generators (www.lpm.org)
  19. ^ Eli Hiller/For The Washington Post via Getty Images (www.gettyimages.com)
  20. ^ specific rate plan for data centers (www.aepohio.com)
  21. ^ approved (www.floridapsc.com)
  22. ^ agreement (www.floridapsc.com)
  23. ^ way they use (www.texastribune.org)
  24. ^ make money based on their flexibility (www.texastribune.org)
  25. ^ being implemented in Missouri (www.ksdk.com)

Authors: Theodore J. Kury, Director of Energy Studies, University of Florida

Read more https://theconversation.com/data-centers-need-electricity-fast-but-utilities-need-years-to-build-power-plants-who-should-pay-271048

Magazine

Bencana membuat anak rentan putus sekolah. Apa solusinya menurut riset?

● Bencana meningkatkan risiko anak putus sekolah, jadi pekerja usia dini, hingga mengalami trauma psikologis.● Bencana juga memperlebar ketimpangan pendidikan, terutama bagi anak miskin da...

Siklon yang ‘lemah’ kini bisa memicu banjir mematikan: Dampak nyata perubahan iklim dan pemanasan laut

Pekan terakhir November lalu, sejumlah negara di Asia tenggara dan selatan porak-poranda akibat bencana yang menerjang sejumlah wilayah di negara tersebut. Warga Sri Lanka, Indonesia and Thailand tere...

Penipuan WO Ayu Puspita mirip skema Ponzi, masyarakat perlu waspada

● Pemilik ‘wedding organizer’ atau WO Ayu Puspita jadi tersangka penipuan senilai Rp16 miliar.● Modus WO Ayu Puspita mirip skema Ponzi yang merugikan konsumen.● Ada tiga ...

hacklink hack forum hacklink film izle hacklink หวยออนไลน์matbetPusulabetสล็อตเว็บตรงgamdom girişpadişahbetMostbetpradabetjojobetartemisbet girişslot888trendbetligobetpusulabet girişmarsbahis girişcasibom girişcasibom giriştürk ifşaBets10matbetMavibet色情 film izlekralbetnakitbahisjojobetYakabet1xbet girişjojobetGrandpashabetbetofficezbahis türkiyematadorbet adresienjoybetpradabetkingroyalkralbet girişgiftcardmall/mygiftultrabetbets10 girişroyalbetmamibetkingroyalcasibomkingroyalbetistugwin288casibomcasino sitelericasibom girişJojobetkingroyal girişkingroyalcasibom girişdeneme bonusumeritkingwinxbetcasibomcasibom girişwbahiswbahisyakabetCasibomBetpuanselçuksportsUltrabet girişDinamobetmasterbettingVdcasinoSekabet girişMarsbahisbetkolikbahiscasinoholiganbetmadridbetholiganbetselcuksportsbetcioyakabetyakabetyakabetjojobetbetpuanyakabetsahabetpacho casinoaertyercasibomvbetcolor pickermeritbet girişkralbet girişultrabet girişultrabet girişultrabet girişbetnano girişcratosslot girişMarsbahisdeneme bonusu veren siteleronwin girişmeritbetultrabetantalya escorttimebetbahsegelultrabetultrabetultrabet girişbahiscasinobahiscasinoultrabetbets10matbetroyal reelsultrabet 2026Kayseri Escortjojobet girişjojobetgrandpashabetbeylikdüzü escortŞişli Escortbettiltcasibom güncel girişMavibetaviator gametimebetbahislionistanbul escort telegramcasibomvaycasinoholiganbet girişsatın almarsbahisbetcioholiganbet girişkavbet girişpadişahbetcasibomgiftcardmall/mygiftttpat.com링크모음주소모음 주소킹주소모음 주소모아eb7png pokiesbest online casino australiabest online pokies australiabcgame96 casinocrown155 hk casinobest online casino in cambodiaMavibetStreameastgalabetmarsbahisgalabetholiganbet girişjojobetcasibombets10 girişbets10 girişMMA Streamjojobet girişJojobetmatbetvdcasinocasibomcasibom girişasdsadasdasdasdasfdasfasfsadfasdfsdfasdasdasdasdkingroyal girişjojobetbahiscasinograndpashabetpin upmamibetslot gacorcasibombetasusmeritbetcasibompusulabetcanlı maç izlesahabet giriscratosroyalultrabetultrabetแทงหวย24meritkingjojobet